CHAPTER 71— CONTRACT DISPUTES

(a) Any judgment against the Federal Government on a claim under this chapter shall be paid promptly in accordance with the procedures provided by section 1304 of title 31.
(b) Any monetary award to a contractor by an agency board shall be paid promptly in accordance with the procedures contained in subsection (a).
(c) Payments made pursuant to subsections (a) and (b) shall be reimbursed to the fund provided by section 1304 of title 31 by the agency whose appropriations were used for the contract out of available amounts or by obtaining additional appropriations for purposes of reimbursement.
(d)(1) Notwithstanding subsections (a) to (c), any judgment against the Tennessee Valley Authority on a claim under this chapter shall be paid promptly in accordance with section 9(b) of the Tennessee Valley Authority Act of 1933 (16 U.S.C. 831h(b)).
(d)(2) Notwithstanding subsections (a) to (c), any monetary award to a contractor by the board of contract appeals of the Tennessee Valley Authority shall be paid in accordance with section 9(b) of the Tennessee Valley Authority Act of 1933 (16 U.S.C. 831h(b)).

Notes

Historical and Revision Notes RevisedSectionSource (U.S. Code)Source (Statutes at Large) 710841:612.Pub. L. 95–563, § 13, Nov. 1, 1978, 92 Stat. 2389; Pub. L. 104–106, div. D, title XLIII, § 4322(b)(7), Feb. 10, 1996, 110 Stat. 677.