Monitoring Gesetzessammlung

40 USC 3143

US - USC Title 40: Public Buildings, Property, and Works

40 USC 3143

§ 3143 - Termination of work on failure to pay agreed wages

CHAPTER 31— GENERAL › SUBCHAPTER IV— WAGE RATE REQUIREMENTS

Every contract within the scope of this subchapter shall contain a provision that if the contracting officer finds that any laborer or mechanic employed by the contractor or any subcontractor directly on the site of the work covered by the contract has been or is being paid a rate of wages less than the rate of wages required by the contract to be paid, the Federal Government by written notice to the contractor may terminate the contractor’s right to proceed with the work or the part of the work as to which there has been a failure to pay the required wages. The Government may have the work completed, by contract or otherwise, and the contractor and the contractor’s sureties shall be liable to the Government for any excess costs the Government incurs.

Notes

Historical and Revision Notes RevisedSectionSource (U.S. Code)Source (Statutes at Large) 314340:276a–1.Mar. 3, 1931, ch. 411, § 2, 46 Stat. 1494; Aug. 30, 1935, ch. 825, 49 Stat. 1012.
The words “The Government may have the work completed” are substituted for “and to prosecute the work to completion . . . thereby” for clarity.
Verwendung von Cookies.

Durch die Nutzung dieser Website akzeptieren Sie automatisch, dass wir Cookies verwenden. Cookie-Richtlinie

Akzeptieren
Markierungen
Leseansicht